How should a stadium order be decomposed before sourcing begins?
Build the order by work zone and time window. Separate gates, suites, concourses, field access, loading areas, hospitality rooms, parking, and post-event cleanup when their instructions or credentials differ. For each unit, identify the role, quantity, reporting location, arrival time, release condition, attire, equipment, accessibility needs, and approving contact. This reveals conflicts that a single total cannot show. Map dependencies as well. A gate team may need credentials before briefing; a conversion crew may not begin until guests clear; premium hospitality may require venue-specific access. The staffing plan should show those prerequisites and the party responsible for releasing each phase.